Install PC roof panels from the chosen panel-and-profile instructions, with the protected face out and the water path kept open. Before drilling, sign off the roof pitch, supports, sheet direction, edge capture, movement allowance, closures and flashings. A reversed UV face or sheet held too tightly can force rework after the roof is closed.
The four hold points below apply across PC roof-panel systems. The numeric examples and channel details are from the named multiwall guides; solid, corrugated and other profile systems need their own current installation instructions.
Start a roof-panel RFQ See PC roofing options

Four site hold points before the next trade closes the roof
Named-guide figures that show why a generic screw rule fails
For Plaskolite’s POLYGAL multiwall installation guide, the published roof recommendation is 1 inch rise per 12 inches run; it directs the flutes down the slope and the UV-protected side toward the sun. Its worked 4 × 8 ft sheet example across a 110°F temperature difference calculates about 0.198 in width and 0.396 in length of movement. Those dimensions are an example for that guide’s sheet and conditions, not hole diameters or allowances for every PC panel.
The LEXAN THERMOCLEAR guide gives a separate named example: at least 20 mm edge engagement in its glazing frame, while allowing thermal movement, and approximately 3 mm expansion per metre for a 50°C difference. Its sloped-glazing guidance recommends 5° for drainage. Do not combine these two suppliers’ details into an untested hybrid system. Get the current guide for the actual sheet, profile and fastener package.
Use this sequence on site
| Stage | Installer check | Evidence at handover |
|---|---|---|
| Set out supports | Measure purlin/rafter spacing, alignment and roof fall; identify high/low edges and penetrations. | Approved support and roof-section drawing with measured deviations. |
| Cut and orient sheets | Keep masking while marking/cutting; face the identified UV side outward; run multiwall channels down slope and clear chips. | Sheet labels, cut list and first installed panel photo before closure. |
| Fix and seal | Use the selected system’s expansion clearance, edge bite, compatible gasket, screw/washer and tightening method. Do not crush or immobilize the sheet. | Visible fixing/edge sample and the current supplier instruction. |
| Close and inspect | Fit the specified upper/lower channel closures, profiles, laps and flashings; verify gutter drainage, clean debris and remove film as directed. | Completion photos, drainage check and maintenance instructions. |
Do not walk directly on PC roof panels. Use safe access supported by the roof structure according to the selected system and site safety plan. For pitch and ponding, see low-slope PC roof guidance; for loading, see the span guide. SinoPlastix can supply the custom PC sheet and fabrication specified on the drawing; the project engineer, roof-system supplier and installer approve the completed roof.
Send an installation-ready sheet inquiry
We can quote custom PC sheet form, grade, colour, cut size and specified fabrication. Common original reports can be requested privately from sales. Actual price and lead time are confirmed for the order. Fill the brief, click Copy brief, open the RFQ form and paste it into the message field. The text here stays in your browser until you copy it; this page does not submit it.
Common questions
Which side of a PC roof panel faces the sun?
Where the offered sheet has a designated UV-protected face, install that identified face outward. Keep its marking until orientation is checked; follow the exact grade’s current instructions.
Do all PC roof panels need oversized screw holes?
No single diameter applies to every system. Some mechanically fixed sheets need movement at holes, while other systems use glazing bars or clips. Use the chosen panel-and-profile detail for clearance and fastener location.
Can installers walk on multiwall PC sheets?
Do not walk directly on the sheets. Use safe access supported by roof members under the site safety plan and the selected system’s instructions.